Extension of time - approval letter example
Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. This is described as an extension of time (EOT).
When it becomes reasonably apparent that there is, or that there is likely to be, a delay that could merit an extension of time, the contractor gives written notice to the contract administrator identifying the relevant event that has caused the delay.
A formal letter is addressed to the contract administrator requesting the extension of time, and presenting the reasons for the request. This letter is then evaluated before approval or rejection. If it is approved, the letter is given a written answer by the contract administrator and a change order is issued.
Here is an example of an approval letter:
Contractor's Name Contract Name Contract Number I refer to your extension of time claim dated [insert date of the claim]. In accordance with clause [insert the contract clause] of the General Conditions of Contract, the Principal grants extension/s of time: [Insert number of days requested and reasons for the time extension.] The Contractual Completion Date (as previously extended) was [insert contract completion date including previous time extension approvals]. This extension of [number of days] days makes [insert new completion date] the Contractual Completion Date. Signed by, Authorised Person |
[edit] Related articles on Designing Buildings
- Acceleration of construction works.
- Change order.
- Common refusals of extensions of time.
- Compensation event.
- Contract administrator.
- Contract claims.
- Delay damages.
- Extension of time.
- How to prepare a claim for an extension of time.
- Practical completion.
- Project programme.
- Time Risk Allowance TRA.
- Variations.
Featured articles and news
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.